Uncontrollable factors of purification workshop engineering


Release time:

2024-03-26

Author:

Source:

The uncontrollable factors of Guangdong purification workshop project are due to the change of subjective and objective conditions in the process of project implementation, which is positive and constant, which is relative. In the process of project progress, the balance is temporary and unbalanced, which is eternal. Therefore, the dynamic control of project objectives must be carried out with the change of situation in the process of project implementation.

Uncontrollable factors of purification workshop engineering

The uncontrollable factors of Guangdong purification workshop project are due to the change of subjective and objective conditions in the process of project implementation, which is positive and constant, which is relative. In the process of project progress, the balance is temporary and unbalanced, which is eternal. Therefore, the dynamic control of project objectives must be carried out with the change of situation in the process of project implementation. In the process of project implementation, the planned value and actual value of the project target are regularly compared. When the deviation of the project target is found, corrective measures should be taken in time. At the same time, in order to avoid the deviation of the project target to the greatest extent, active control measures are actively taken, that is, various influencing factors that may lead to the deviation of the project target are analyzed in advance, and effective preventive measures are taken for these factors.
Decomposition of Construction Progress Target of Purification Workshop by Layer
1) The layer-by-layer decomposition of the construction progress target of the purification workshop is from the beginning of the construction of the purification workshop and in the construction process of the purification workshop, gradually from macro to micro, from coarse to fine to prepare the progress plan process of different concentrations.
2) Dynamic tracking and control of the construction progress target of the purification workshop during the construction of the purification workshop.
① Collect the actual value of the construction progress of the purification workshop according to the requirements of progress control.
② Regularly compare the planned and actual values of the construction progress of the Guangdong purification workshop. According to the characteristics of this project, the schedule control cycle can be set at one ten-day or half-month. When comparing the planned value and actual value of the construction progress of the purification workshop, it should be noted that the corresponding project content should be consistent, such as the progress target value of the milestone event or the progress target value of the further refinement as the planned value of the progress, the actual value of the progress is relative to the milestone event or the actual progress of the sub-item work.
The comparison between the planned value and the actual value of the progress should be a quantitative data comparison, and the result of the comparison is the progress tracking and control report. Such as the preparation of progress control of the ten-day, monthly, quarterly, semi-annual and annual reports.
③ Through the comparison of the construction schedule value and the actual value of the purification workshop, if the deviation of the progress is found, the corresponding corrective measures must be adopted to correct the deviation.
3) If necessary (I. e., it is found that the original purification workshop construction progress target is unreasonable, or the original purification workshop construction progress target cannot be achieved, etc.), adjust the Guangdong purification workshop construction progress target.
(1) The layer-by-layer decomposition of the construction cost target of the purification workshop, through the preparation of the construction cost plan of the purification workshop, analyze and demonstrate the possibility of achieving the construction cost target of the purification workshop, and decompose the construction cost target of the purification workshop.
(2) Dynamic tracking and control of the construction cost target of the purification workshop during the construction of the purification workshop.